Review of project planning methods for deconstruction projects of buildings

Hübner, Felix 1; Volk, Rebekka ORCID iD icon 1; Kühlen, Anna 1; Schultmann, Frank ORCID iD icon 1
1 Institut für Industriebetriebslehre und Industrielle Produktion (IIP), Karlsruher Institut für Technologie (KIT)

Abstract:

The paper aims to provide a comprehensive overview of literature and methods that can be used for deconstruction project planning of buildings. Furthermore, shortcomings of the identified planning methods are presented and research gaps are identified.
Requirements to consider for the planning of deconstruction projects are defined, to help in the classification of planning methods. With the help of these requirements, in a detailed literature review strategic and operational planning methods for deconstruction projects are investigated and discussed. Requirements which are not met by any of the identified planning methods can be interpreted as research and/or documentation gaps.
On the one hand, the literature review shows that recent approaches deal with planning methods for deterministic time and resource scheduling. Furthermore, project costs can be well planned by several methods. On the other hand, the literature review reveals that recent approaches mostly do not consider risks and uncertainties, environmental hazards or specific safety issues. A major shortcoming is that applied planning methods can only calculate up to a specific level of detail, e.g. ... mehr


Volltext §
DOI: 10.5445/IR/1000068185
Originalveröffentlichung
DOI: 10.1108/BEPAM-11-2016-0075
Scopus
Zitationen: 21
Dimensions
Zitationen: 18
Cover der Publikation
Zugehörige Institution(en) am KIT Institut für Industriebetriebslehre und Industrielle Produktion (IIP)
Publikationstyp Zeitschriftenaufsatz
Publikationsjahr 2017
Sprache Englisch
Identifikator ISSN: 2044-124X
urn:nbn:de:swb:90-681859
KITopen-ID: 1000068185
Erschienen in Built environment project and asset management
Verlag Emerald
Band 7
Heft 2
Seiten 212-226
Schlagwörter Planning; Planning Methods; Deconstruction; Deconstruction Planning; Deconstruction Planning Methods; Building Deconstruction Planning; Deconstruction scheduling
Nachgewiesen in Dimensions
Scopus
KIT – Die Forschungsuniversität in der Helmholtz-Gemeinschaft
KITopen Landing Page